Aug 11

Project Update

Posted on August 11, 2023 at 12:50 PM by Cheryl Malikowski

Utilities are complete along Wilson Avenue between Highway 23 and East St. Germain Street. Road reconstruction is ongoing.

The portion of Wilson Avenue from Highway 23 to 1st Street SE will be open to local traffic by approximately August 25th, weather permitting. Through traffic will not be allowed in this portion at this time.

Work continues on Wilson Avenue between East St. Germain Street to 1st Street NE and remains closed.


Jul 24

Project Update

Posted on July 24, 2023 at 11:54 AM by Cheryl Malikowski

The intersection of East St. Germain Street and Wilson Avenue is reopened with a single lane of traffic in each direction.

Recently, Wilson Avenue from East St. Germain Street to 1st Street NE was also closed for construction work. 

Jul 14

Project Update

Posted on July 14, 2023 at 2:27 PM by Cheryl Malikowski

The project is coming along.  The contractor has the utilities completed in the first two blocks of Wilson Avenue.  The intersection of East St. Germain Street and Wilson Avenue should be open by mid to late July.

Wilson Ave 7-14-23